The scene reproduces the Vardar River crossing, DN 700. The terrain and strata come from the interpretative lithological profile, the section face is the drawing at true size, and the bore follows the designed profile. Existing utilities, land parcels, the water level and the equipment are schematic; the rig is an American Augers DD600, modelled from catalogue data.
The 3D scene requires WebGL 2. The full text of the process is available below.
From ground to pipeline
Investigation, design and horizontal directional drilling for natural gas and crude oil transmission pipelines
We survey the route, check the legal and zoning status of the land and the clearances to existing utilities, investigate the site by geophysical and geotechnical methods, design the pipeline and its horizontal directional drilling crossings, and provide technical assistance during construction. We work in Romania, Bulgaria and North Macedonia.
Topographic survey
We survey the pipeline corridor and the entry and exit areas of the bore with GNSS receivers and a total station, in the national projection system (Stereo 70 in Romania). The measured points give the site plan and the digital terrain model, on which the longitudinal profile of the bore is laid out.
- site plan
- coordinate schedule
- digital terrain model
Land status along the route
For every property affected by the corridor we check the land register and the cadastral plan, the zoning regime, protected natural areas and flood zones. We draw the constraints on the site plan before the route is fixed, so that the rig pad, the mud pits and the string assembly lane sit on land for which access and construction rights can be obtained.
- legal status of the properties
- constraints on the plan
- permits and approvals required
Coexistence with existing infrastructure
Pipelines, cables, overhead power lines, roads, railways and canals in the vicinity are drawn on the plan with their protection and safety zones. Clearances and crossing angles are checked against the codes in force for each utility. For the bore, the distance to neighbouring steel pipelines also matters, since they disturb the magnetic steering of the bit. Where proximity cannot be avoided, we design the protection of the existing utility; at Balș we designed the protection of the DN150 and DN600 gas pipelines at a 110 kV underground power cable.
- networks on the plan
- clearances checked against the codes
- protection details
Geophysical survey
The crossing section is investigated by geophysical methods suited to the stratification intercepted by the geotechnical boreholes. High-resolution seismic reflection gives the geometry of the strata beneath the riverbed, seismic refraction gives the P-wave velocities, MASW and MAM give the shear-wave velocity (Vs) profile, and electrical resistivity tomography delineates the strata by resistivity contrast and reveals the saturated zones.
Methods applied at the Vardar River, at the Poarta Albă – Midia Năvodari canal and at Kozloduy, where the MASW and MAM lines had a minimum target depth of 225 m.
- seismic sections
- resistivity tomograms
- Vs profiles
Geotechnical boreholes
Geotechnical boreholes and dynamic probing give the stratification, the grain-size distribution, the SPT N-values and the design geotechnical parameters of each stratum. We correlate the layer boundaries interpreted on the geophysical sections with the lithology logged in the boreholes and calibrate the geophysical interpretation on them, so that every unit of the lithological profile has samples and tests from a borehole.
Boreholes and probing carried out on Lot 3 of the Vertical Corridor, Rupcha – Vetrino, and at the Vardar River.
- borehole logs
- design geotechnical parameters
- geotechnical report
Lithological profile and hydrology
The geophysical data and the boreholes are interpreted together in the lithological profile, with the units followed along the whole length of the crossing. We select the host stratum from the profile on the basis of hole-wall stability and formation permeability, which governs the risk of drilling-fluid losses. The hydrological study gives the design discharge and the scour depth, and the pipeline cover is measured from the design scour level.
- interpretative lithological profile
- design scour level
- host stratum
Pipeline and HDD design
On the lithological profile we lay out the bore, with entry and exit points and angles, bend radii and the horizontal section in the selected stratum. We check pullback force, installation stresses in the pipeline, buoyancy and ballasting of the string, and the annular pressure of the drilling fluid against the fracture pressure of the ground. Outside the crossing the pipeline is laid in trench, to ANRE Order 118/2013 for natural gas and to the CONPET standards for crude oil. The design starts from the site plan and comprises the longitudinal profile, construction details, technical reports and calculation notes.
- route and longitudinal profile
- design checks
- construction details
The rig
The bore is designed for the class of rig that will drill it. The rig in the scene is an American Augers DD600, modelled from the manufacturer's catalogue: 272 t thrust and pullback force, 135,581 Nm rotary torque and an entry angle adjustable between 8.5 and 18°. The computed pullback force, the drilling-fluid flow rate and pressure are checked against these limits.
- pullback force against rig capacity
- entry and exit angles
- mud pump flow rate and pressure
Pilot hole
The pilot bore leaves the entry point and follows the designed profile to the exit point. The drill string, with a jet bit or a mud motor, is pushed and rotated by the rig, and the bit position is surveyed at every joint, by a wireline steering system with a surface coil or, next to steel pipelines, by gyroscopic steering. At the Vardar River the drilled length is 554.27 m, with 900 m radii, a 10° entry, an 8° exit and the horizontal section at elevation 31.00, in unit L3.
- bit and mud motor
- steering and survey of the drilled path
Reaming
The pilot hole is reamed in one or more passes to the final diameter, with the reamer pulled from the exit towards the rig. The bentonite-based drilling fluid supports the hole wall and carries the cuttings to the mud pit; after the recycling unit the cleaned fluid returns to the circuit. The annular pressure is kept below the fracture pressure of the ground, so that the fluid does not break out at the surface or into the riverbed. For the Ø711 mm pipeline, the verification report took a final hole of Ø1067 mm.
- successive reaming passes
- closed-loop drilling-fluid system
- annular pressure below the fracture pressure
Pullback
The string is welded on the exit side and laid on rollers. At pullback, the pulling head and the swivel connect the string to the reamer, and the rig pulls the string through the fluid-filled hole to the entry point. At both ends the string is tied in to the trenched pipeline. From string preparation to pullback we provide the contractor with technical assistance and construction consultancy. The five crossings on the Kulata – Kresna looping were built as designed.
ANRE licence ET 24543 covers the construction of natural gas transmission systems.
- pilot hole
- reaming
- pullback
- technical assistance
Pipeline in service
The Ø711 × 14.2 mm L450 pipeline remains in the selected stratum beneath the riverbed, with the cover checked stake by stake against the ground surface and the stratum boundaries. On both sides of the crossing the route continues in trench.
- as-built profile
- documents for acceptance
The interpretative lithological profile
The section face in the scene reproduces the project drawing, the interpretative lithological profile of the Vardar River crossing, at the same horizontal and vertical scale, with the designed bore drawn over the lithological units. The full drawing can be read in the next section.
- interpretative lithological profile
- designed bore on the profile
Lithological profiles and designed bores
Three horizontal directional drilling crossings, each with the designed bore drawn on the interpretative lithological profile. The drawings are read horizontally, from one end to the other, as the page scrolls.
Vardar River, DN 700 gas, North Macedonia
The interpretative lithological profile of the crossing, compiled from seismic and geoelectrical surveys, dynamic probing and six geotechnical boreholes, at the same horizontal and vertical scale. We drew the bore from the final verification report over the profile.

Lithological units
L1 · Sand with gravel
Gravel with sand, with sand and silty sand within the first 3 m, locally sand with gravel, yellow brown, generally loose, locally medium dense at the base. The formation is unstable, with high risk for drill hole collapse. The formation has high permeability, with high risk for drilling fluid losses.
Density 1.90 g/cm³ · NSPT 8–11
L2 · Gravel with sand
Gravel with sand, with rare boulders, locally with silty-clayey binder, brown, dense. The formation is mostly stable, with low to medium risks for drill hole collapse. The formation has moderate permeability, with medium risks for drilling fluid losses.
Density 2.05 g/cm³ · NSPT 47–59
L3 · Sand with gravel, with silty-clayey binder
Medium to coarse sand with fine gravel, with silty-clayey binder, grey. The formation is very dense, with strong binder between clasts. The formation is stable, with very low risks for drill hole collapse. The formation has low permeability, with low risks for drilling fluid losses.
Density 2.20 g/cm³ · NSPT = R (refusal)
Designed profile
- Pipe
- Ø711 × 14.2 mm, L450
- Length
- 554.27 m drilled; 552.03 m in plan
- Entry
- ch 103.63, el. 49.64, at 10°
- Exit
- ch 655.66, el. 48.33, at 8°
- Radii
- 900 m
- Horizontal section
- el. 31.00, in unit L3
- Final hole
- Ø1067 mm
- Document
- VRD-HDD-DES-001 Rev. 0
The Danube at Cernavodă, Ø20 in and Ø28 in crude oil, CONPET S.A.
Three parallel bores of 1,466.0 m each, for the Ø20 in and Ø28 in crude oil pipelines and for the Ø219.1 mm process line, which carries the drilling fluid between exit and entry and is used as a magnetic reference for steering the drill string. The design placed the rig on the right bank, at Cernavodă, and the string assembly on the left bank, at Stelnica. Because of the existing pipelines in the corridor, the pilot bore was designed with gyroscopic, non-magnetic steering. On the drawing, the red line represents the designed bore, about 20 m below the thalweg.


From the detailed design
- Pipelines
- Ø508 × 14.2 mm L360NE; Ø711 × 16 mm L360N
- Mud line
- Ø219.1 × 8.0 mm
- Length
- 1,466.0 m drilled for each bore; 1,462.5–1,462.8 m in plan
- Radius
- 1,500 m
- Below the riverbed
- top of pipe 19.6–19.8 m below the thalweg; pipe axis 20.0–30.8 m below the bed
- Design discharge
- Q1% = 7,870 m³/s
- Pilot steering
- gyro, non-magnetic
- Drawing
- no. 23A of the detailed design, 2022
The Borcea branch at Fetești, Ø20 in and Ø28 in crude oil, CONPET S.A.
On the same Constanța – Bărăganu route, the Borcea branch was crossed to the same scheme, with the two crude oil pipelines and the process line drilled in parallel, with 1,500 m radii. The design placed the rig on the left bank and the string assembly on the right bank. The six bores at the Danube and at the Borcea were drilled in three months.


From the detailed design
- Pipelines
- Ø508 × 14.2 mm L360NE; Ø711 × 16 mm L360NE
- Mud line
- Ø219.1 × 8.0 mm
- Drilled length
- 1,258.0 m (Ø20 in); 1,263.0 m (Ø28 in); 1,257.0 m (mud line)
- Radius
- 1,500 m
- Below the riverbed
- top of pipe 19.6–19.8 m below the thalweg; pipe axis 20.0–34.3 m below the bed and 7.4–7.6 m below the crest of the right-bank levee
- Design discharge
- Q1% = 9,540 m³/s
- Pilot steering
- gyro, non-magnetic
- Drawing
- no. 22A of the detailed design, 2022
The Danube and Borcea crossings in the press
- World Pipelines, 05.05.2023: A pipeline journey across the Danube River
- Energy Industry Review, 04.04.2023: One of CONPET's Main Investment Objectives Completed
- The Diplomat Bucharest, 03.04.2023: CONPET completes works to replace the connecting lines under the Danube and the Borcea branch
What we check on the profile
The bore profile is drawn on the interpreted geological section, with the host stratum selected from the investigation. Each check is based on a guideline or standard of European horizontal directional drilling practice, in the edition in force at the date of the design.
Profile geometry
Entry and exit angles, minimum bend radius, cover below the design scour level and an alignment kept within the selected stratum. At the Vardar River, the 900 m radius satisfies the condition R ≥ 1 200 · OD for the Ø711 mm pipeline.
DCA Technical Guidelines, 5th ed. (2025)Pullback force
Segmented model, computed element by element from the pulling head to the end of the string, with friction on the hole wall, the capstan effect in the bends and the viscous drag of the drilling fluid.
ASTM F1962-22, adapted to steel · PRCI · ASCE MOP 108, 3rd ed. (2024)Installation stresses and strains
Tensile stress, bending in the curves and external pressure, checked in combination, together with the collapse resistance of the wall.
NEN 3650-2:2020+A1:2024 · API 5C3 / ISO 10400Buoyancy
Apparent weight of the pipeline in the drilling fluid and the ballasting of the string, which reduces the net buoyancy and, through it, the friction on the hole wall, keeping the pullback force within the rig's capacity.
ASCE MOP 108 · DCA Technical GuidelinesDrilling-fluid pressure
Maximum allowable ground pressure along the bore, compared with the annular pressure required for fluid circulation, so that the fluid neither fractures the ground nor reaches the surface or the riverbed.
NEN 3651:2020 · Luger & Hergarden, Delft Geotechnics (1988)Line pipe
Wall thickness, steel grade and design pressure, to the code of the country where the line is built.
EN 1594:2024 · API 5L · SR EN ISO 3183 · ANRE Order 118/2013 · CONPET standardsAmerican Augers DD600
The rig in the scene is rebuilt to its catalogue dimensions. The values below come from the manufacturer's brochure and represent the limits against which the calculation of a bore designed for a rig of this class is checked.
Source: American Augers, DD600 brochure (2023). American Augers and DD600 are trademarks of their respective owners. The 3D model is a simplified reconstruction, with no commercial link to the manufacturer.
| Parameter | Catalogue value |
|---|---|
| Thrust and pullback | 600,000 lb (272 t) |
| Carriage | 4 pinions, up to 37 m/min (120 ft/min), 3 speed ranges |
| Rotary | 135,581 Nm (100,000 ft·lb), up to 130 rpm |
| Engine | Cat C18, 578 kW (755 hp) |
| Drilling fluid | 3,122 L/min (825 gpm) at 103 bar (1,500 psi); 88.9 mm fluid course |
| Wrenches | clamp range Ø89–286 mm; breakout 329,465 Nm; makeup 246,760 Nm |
| Drill pipe | Range II |
| Entry angle | 8.5–18° |
| Cab | separate, 3.66 m or 6.10 m (12 ft or 20 ft) |
| Dimensions | 16 × 2.54 × 3.51 m; 43 t (95,000 lb) with wrenches and fluids |
The data the profile rests on
The geophysical methods cover the route continuously between boreholes, and the geotechnical boreholes calibrate them. Their correlation gives the interpretative lithological profile on which the directional bore is designed.
| Method | Result | Where we applied it |
|---|---|---|
| High-resolution 2D seismic reflection | geometry of the layers and contacts beneath the river bed | Vardar River; Poarta Albă – Midia Năvodari canal |
| Seismic refraction | P-wave velocities and depth to the stiff layers | Vardar River |
| MASW and MAM | shear-wave velocity (Vs) profile with depth | Vardar River; Kozloduy, to a 225 m target depth |
| Downhole seismic | wave velocities measured in the borehole, with a 500 kg gravity source | Kozloduy, Units 7 and 8 |
| Geoelectrical surveys (resistivity tomography and vertical electrical sounding) | lithological contrasts and saturated zones | Vardar River; Vertical Corridor, Rupcha – Vetrino |
| Geotechnical boreholes, dynamic probing | stratification, grain size and design geotechnical parameters | Rupcha – Vetrino; Vardar River |
| Hydrological study | design discharges and scour depth | Poarta Albă – Midia Năvodari canal |
| Thermal resistivity | heat dissipation around a cable installed by HDD | Copșa Mică solar plant connection |
Portfolio of horizontal directional drilling works
A selection of works documented by contract or by the design documents, in reverse order of the contract year. The last column states the company's contribution to each project.
| No. | Obstacle crossed | Pipeline or line | Country | Year | Company contribution |
|---|---|---|---|---|---|
| 1 | DN150 Iancu Jianu – Balș gas pipeline | 110 kV underground power cable | RO | 2026 | design |
| 2 | Vardar River | gas, DN700 Gevgelija – Negotino, Ø711 × 14.2 mm | MK | 2026 | HDD design and verification report; geophysical and geotechnical study |
| 3 | Olt River, at Ostroveni | gas, branch line to DN400 Govora – Drăgășani | RO | 2026 | geotechnical and geophysical studies; design; supervision |
| 4 | Poarta Albă – Midia Năvodari canal | crude oil, 14 and 28 in Constanța – Bărăganu | RO | 2025 | hydrological and geotechnical studies; geophysics including seismic reflection |
| 5 | Golyama Kamchiya River, km 22+909 | gas, DN1200 Rupcha – Vetrino, Ø1219 × 17.5 mm | BG | 2025 | geotechnical boreholes; geophysical and geotechnical study; HDD design; construction support |
| 6 | Glavnitsa River, km 37+149 | gas, DN1200 Rupcha – Vetrino, Ø1219 × 17.5 mm | BG | 2025 | geotechnical boreholes; geophysical and geotechnical study; HDD design; construction support |
| 7 | Provadiyska River, km 51+453 | gas, DN1200 Rupcha – Vetrino, Ø1219 × 17.5 mm | BG | 2025 | geotechnical boreholes; geophysical and geotechnical study; HDD design; construction support |
| 8 | Route of the Copșa Mică solar plant cable connection | underground power cable | RO | 2025 | geotechnical, geological and geophysical study; interpretative lithological profile for HDD |
| 9 | Struma River, km 1+500 | gas, DN700 Kulata – Kresna, Ø711 × 14.2 mm | BG | 2025 | geotechnical and geophysical study; HDD design, built as designed; construction support |
| 10 | Struma River, km 4+500 | gas, DN700 Kulata – Kresna | BG | 2025 | geotechnical and geophysical study; HDD design, built as designed; construction support |
| 11 | Struma River, km 7+300 | gas, DN700 Kulata – Kresna | BG | 2025 | geotechnical and geophysical study; HDD design, built as designed; construction support |
| 12 | Strumeshnitsa River, km 13+100 | gas, DN700 Kulata – Kresna | BG | 2025 | geotechnical and geophysical study; HDD design, built as designed; construction support |
| 13 | Struma River, km 45+500 | gas, DN700 Kulata – Kresna | BG | 2025 | geotechnical and geophysical study; HDD design, built as designed; construction support |
| 14 | Salina Turda, network of 12 drains | drains for infiltration water | RO | 2022 | geotechnical and geophysical study; design |
| 15 | Danube River, at Cernavodă (C1–C2) | crude oil, Ø20 in and Ø28 in Constanța – Bărăganu | RO | 2021 | geotechnical and geophysical studies; design; permitting; construction support |
| 16 | Borcea branch, at Fetești (C3–C4) | crude oil, Ø20 in and Ø28 in Constanța – Bărăganu | RO | 2021 | geotechnical and geophysical studies; design; permitting; construction support |
RO Romania · BG Bulgaria · MK North Macedonia. Items 5–7 and 9–13 belong to the Vertical Gas Corridor (Bulgartransgaz EAD), item 2 to the Greece – North Macedonia interconnector.
Selected works
For the larger infrastructure projects that include our work, we link to the press coverage and to the releases of the transmission operators and of the financing institutions.
The articles describe these projects as a whole; the company's contribution is the one recorded on each project sheet.
International
Vertical Gas Corridor, Kulata – Kresna looping, Bulgaria
Five horizontal directional drilling crossings of the Struma and Strumeshnitsa rivers, on the pipeline that increases the transmission capacity between Greece and Bulgaria. We carried out the geotechnical and geophysical studies, designed the bores and provided construction consultancy. The crossings were built as designed.
- Pipeline
- DN700; at km 1+500, Ø711 × 14.2 mm, L415ME
- Locations
- Struma km 1+500, 4+500, 7+300, 45+500; Strumeshnitsa km 13+100
- Year
- 2025
- Bulgartransgaz, press release, 06.06.2024: contracts signed for the Kulata – Kresna and Rupcha – Vetrino loopings
- SeeNews, 06.06.2024: Bulgartransgaz signs 248 mln euro deals for Vertical Corridor expansion
- Bloomberg, 28.03.2025: Bulgaria to Press Ahead With Gas Grid Expansion, Minister Says
- Pipeline & Gas Journal, 04.06.2026: Bulgaria Advances Vertical Gas Corridor, Expands Greece Pipeline Capacity
Vertical Gas Corridor, Lot 3, Rupcha – Vetrino, Bulgaria
Three river crossings on the pipeline that doubles Bulgaria's exit capacity towards Romania at the Negru Vodă / Kardam point. The work started with the geotechnical boreholes, continued with the geophysical and geotechnical study and covers the design of the directional bores and construction consultancy.
- Pipeline
- DN1200, Ø1219 × 17.5 mm, L450ME
- Locations
- Golyama Kamchiya km 22+909; Glavnitsa km 37+149; Provadiyska km 51+453
- Years
- 2025–2026
Vardar River crossing, Greece – North Macedonia interconnector
Design of the directional bore on the Gevgelija – Negotino section and the final verification report issued before drilling, based on the geophysical and geotechnical study of the route. The study comprised high-resolution 2D seismic reflection, seismic refraction and MASW, geoelectrical surveys, dynamic probing, geotechnical boreholes and the interpretative lithological profile.
- Pipeline
- DN700, Ø711 × 14.2 mm, L450
- Geometry
- 552.03 m in plan; 554.27 m drilled; R 900 m
- Document
- VRD-HDD-DES-001
- Year
- 2026
- European Investment Bank, press release, 23.12.2021: financing of the Gevgelija – Negotino section
- Argus Media, 12.07.2021: Greece, North Macedonia sign deal for gas line
- Balkan Green Energy News, 30.10.2023: final investment decision
- Enerdata, 12.05.2025: construction contract for the North Macedonian section
Kozloduy Nuclear Power Plant, Units 7 and 8, Bulgaria
Geological and geophysical study of the site of the two AP1000 units, comprising MASW and MAM seismic surveys on four lines to a minimum target depth of 225 m, seismic source generation for the downhole tests and integrated interpretation with the geotechnical boreholes.
- Methods
- MASW; MAM; downhole
- Source
- gravity drop, 500 kg (boreholes 3 and 4, 150–30 m)
- Year
- 2025
Romania
Danube at Cernavodă (C1–C2) and Borcea branch at Fetești (C3–C4), imported crude oil lines
Replacement by horizontal directional drilling of the crossing lines of the Constanța – Bărăganu pipelines, in place of the 12¾ in lines from 1968–1978. We carried out the geotechnical and geophysical studies and the design, handled the permitting and provided technical assistance; the six bores were drilled in three months. The work was presented together with Horizontal Drilling International at the DCA Europe annual congress.
- Pipelines
- crude oil, Ø20 in and Ø28 in
- Bores
- 6, drilled in three months
- Years
- 2021–2023
Salina Turda, drainage of infiltration water
Geotechnical and geophysical study and design of a network of 12 drains installed by horizontal directional drilling, for the long-term drainage of the western overburden hill.
- Drains
- 12, by directional drilling
- Year
- 2022
Poarta Albă – Midia Năvodari canal, 14 and 28 in crude oil lines
Hydrological and geotechnical studies and geophysical surveys, with seismic reflection, for the replacement by horizontal directional drilling of the Constanța – Bărăganu pipelines at the canal crossing.
- Pipelines
- crude oil, 14 and 28 in
- Stage
- approvals, March 2026
- Years
- 2025–2026
In 2026 we are also designing the diversion of the Ø20 in Bărăganu – Onești crude oil line at the Focșani – Brăila expressway and the replacement of about 3 km of the Ø10¾ in crude oil line at Independența, both for CONPET S.A., and the protection of the DN150 and DN600 gas pipelines at the 110 kV underground cable in Balș.
Our work in the field
Photographs from the sites where we provided technical assistance or construction consultancy, from string preparation to pullback through the drilled hole.






Due diligence, operating pipelines and water
Besides the design of horizontal directional drilling crossings, we serve investors who buy or develop land, projects in the permitting stage and works located near transmission pipelines or watercourses. Each service can be contracted separately, for a single site or for a portfolio of sites.
Due diligence for land and projects
Preliminary screening of candidate sites
When an investor is considering several sites, we run a quick check of each site against the land book extract and public sources. The screening helps the investor choose the sites for which full due diligence is justified.
- plot boundary, rebuilt from the land book extract and georeferenced
- zoning regime under the documentation in force
- nearby gas and crude oil transmission pipelines and power lines
- protected natural areas, flood zones and aeronautical easements
- road access
- a favourability note for each site, by criteria
Site due diligence, technical and legal
For the selected site we establish what can be built, which restrictions encumber it and what must be obtained before permitting. Each restriction is recorded with the measured distance, the affected area and the regulation that imposes it.
- existing networks and installations on and around the site
- protection and safety zones of gas and crude oil transmission pipelines and power networks
- technical constraints of the site, arising from roads, railways, water, protected areas and airspace
- cadastral and land book documentation, with encumbrances and the owner's position
- zoning regime, need for a zonal plan (PUZ) and validity of the zoning documentation
- inventory of required approvals and consents
- legal opinion, issued by our partner attorney, where the order requires it
- due diligence report, drawings and GIS data (KMZ, GeoJSON), in Romanian and, on request, in English
- on lenders' request, a reliance letter
Documentary due diligence of projects in permitting
When a project already holds an urban planning certificate, approvals, a grid connection permit or a building permit, we check whether the documents cover the current situation of the land. The service is intended for investors, advisers and lenders taking over a project.
- inventory of the documents received and list of missing documents
- up-to-date land book extracts for every plot occupied or crossed, checked against the urban planning certificate, the site plan and the ANCPI geoportal; we flag plots renumbered after systematic registration and plots crossed but missing from the certificate
- plot register, with the deed that grants access and construction rights for each item and the items not covered
- answers to advisers' and lenders' questions and to the risk matrix, with the action needed for each risk
- on request, technical review of the design, cost–benefit analysis, construction risk and project vulnerabilities
- plot register in Excel, Q&A note and due diligence report
Zonal plan, utilities and permit tracking
After the land purchase, we assist the investor until the building permit is issued.
- design brief for the PUZ
- review of the documents prepared by the investor's designers for the PUZ approvals
- meetings with the designer and the authorities
- review of the final documentation before it is filed for approval
- possible connection points for power, gas, water and sewerage, and stormwater discharge
- land improvement works (ANIF) on the site and their constraints
- preliminary solutions note, ahead of the operators' connection procedure
- validity of approvals and consents, authority deadlines and land book changes on the affected plots, with a change note at the agreed interval
Operating transmission pipelines
Diverting and making safe transmission pipelines
A new road, a substation, a housing area or a warehouse may fall within the protection zone or the safety zone of a natural gas, crude oil, gasoline, condensate or ethane transmission pipeline. For the developer of that work we design the diversion of the pipeline or its protection in place, under the conditions set by the transmission system operator, and obtain the operator's approval of the design.
- we review the operator's location permit and the technical standards applicable to the pipeline
- we locate the pipeline on site together with the operator's field staff, recording its route, depth and test posts, and the findings go into the cooperation note signed with the operator
- we select the solution, whether diversion of the section, casing, concrete slabs or recoating, with the clearances to the new structures checked against the operator's standard
- we prepare the technical design, specifications, construction details, quantities and cost documentation, and defend it before the operator's technical and economic committee
- the diverted route, with profile and bends of at least 5 D on piggable lines
- cased crossings of roads and dikes, by open cut, pipe ramming, auger boring or HDD, with vent, spacers and end seals
- cathodic protection of the casings, with galvanic anodes and test posts
- tie-in programme, with emptying of the line or product transfer, mechanical stoppling, cold cutting and recommissioning
- pressure test of the new section, decommissioning of the old line and return of the recovered pipe to the operator
- gasoline pipeline diversion
- gas pipeline diversion
- lateral diversion
- protection at new road
- dike crossing
- casing
Construction and acceptance support
The designer answers for the solution until acceptance. During construction we stay in contact with the contractor, the operator and the site supervisor.
- attend the critical inspection stages and the pressure test
- issue site instructions where ground conditions differ from the design
- check additional quantities against the bill of quantities
- attend the acceptance and the handover of the diverted pipeline to the operator
Water
Hydraulic studies for watercourse crossings
A pipeline crossing a river or a canal is laid below the depth to which floods can erode the bed. The hydraulic study establishes this scour depth and the bank protection required along the crossing reach.
- we obtain the 1 % and 0.1 % peak discharges from the river basin administration or from INHGA
- we survey river cross-sections upstream and downstream of the crossing
- we compute water levels along the reach, with the backwater of bridges and existing works
- we compute general and local scour and check bank stability
- we place the pipeline below the scour level, with a safety margin, and size the bank protection
- the hydraulic study, with calculations and drawings, used in the design and in the water management file
Water management approval and authorisation
For the works listed in art. 48(1) of the Romanian Water Law no. 107/1996, the location permit and the water management approval are prerequisites for the building permit, under art. 49(31) of the same law. For operation, the water management authorisation is obtained afterwards.
- technical documentation for the water management approval, with the hydraulic study and, where required, the flood risk study
- filing with the river basin administration and answers to its requests, until the approval is issued
- documentation for the water management authorisation, after construction
- clarifying which hydrological data apply when the work holds an older approval
Site investigation and permits
Site investigation
Site investigations are scoped on the basis of the due diligence results, at the points that matter for the project.
- geotechnical studies
- geophysical surveys
- hydrological studies
- topographic surveys
- UXO detection
Approvals, consents and land
A linear project requires approvals from network operators, road and water administrators, environmental authorities and local authorities. We handle them as one file.
- register of existing networks in the corridor, from operator plans and the topographic survey
- each approval condition linked to the design document that meets it
- inventory of affected plots, with temporary and permanent land take
- removal of land from agricultural use
Atanasiu & Skills
Atanasiu & Skills S.R.L., formerly Atanasiu Proiect S.R.L., has worked from Târgoviște since 2019. Design, survey, geophysics and geotechnics work in one team, so the bore profile is drawn on data acquired and interpreted by the people who design it.
The company is led by Eng. Dragoș Alexandru Atanasiu, an engineer in Mining, Petroleum and Gas, specialised in Hydrocarbon Transmission, Storage and Distribution (Lucian Blaga University of Sibiu, top of the graduating class), and an ANRE-licensed PGT designer for natural gas transmission systems. Eng. Atanasiu designed the crossings on the Kulata – Kresna looping and the Vardar River crossing, led Lot 3 of the Vertical Corridor as chief project engineer and was project manager of the geological and geophysical study for Kozloduy Units 7 and 8.
CONPET S.A. rated the company "very good" for design and field studies in recommendation no. 34670 of 02.11.2020. We have been an associate member of DCA Europe since 2023, at the invitation of the association's vice-president.